Roads20JD0005

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS BRGY. ISIS TO BOUNDARY BRGY. LUGDUNGAN LEADING TO LINABO PEAK (3003 STEPS) POLANCO, ZAMBOANGA DEL NORTE

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS BRGY. ISIS TO BOUNDARY BRGY. LUGDUNGAN LEADING TO LINABO PEAK (3003 STEPS) POLANCO, ZAMBOANGA DEL NORTE is a DPWH-tracked public work in Zamboanga del Norte 1st DEO, Region IX. Reported contract value: ₱19,041,141.47. Status: Reported complete (DPWH). Contractor on record: STARS. Figures trace to dpwh.

Zamboanga del Norte 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of flood control structure along Right Bank of Talinga River (downstream), Sindangan, Zamboanga del Norte
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Zamboanga del Norte 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱19,041,141.47

Progress

Reported complete (DPWH)

Start Date

November 26, 2020

Target End

May 19, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.