Buildings and Facilities18KJ0197

CONSTRUCTION OF CLASSROOMS BATCH 1, JACINTO NEMENO ELEMENTARY SCHOOL (2STY6CL), OZAMIZ CITY, MISAMIS OCCIDENTAL

CONSTRUCTION OF CLASSROOMS BATCH 1, JACINTO NEMENO ELEMENTARY SCHOOL (2STY6CL), OZAMIZ CITY, MISAMIS OCCIDENTAL is a DPWH-tracked public work in Misamis Occidental 2nd DEO, Region X. Reported contract value: ₱13,606,681.01. Status: Reported complete (DPWH). Contractor on record: RUDHIL CONST. Figures trace to dpwh.

Misamis Occidental 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control at Layawan River along Ozamiz City-Oroquieta City Road, Oroquieta City, Misamis Occidental
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-18-0018857

₱8,639,025.00 · FY2018

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

1,028 projects · ₱22.5B total · 0 flags

4. Implementation

Contract Amount

₱13,606,681.01

Progress

Reported complete (DPWH)

Start Date

July 30, 2018

Target End

December 16, 2018