Rehabilitation / Major Repair of Flood Control Structure21CJ0007

Rehabilitation of Flood Control Structures along Tarlac River Control Left Dike, Sembrano-Sta. Lucia Section (Phase III), Gerona, Tarlac

Rehabilitation of Flood Control Structures along Tarlac River Control Left Dike, Sembrano-Sta. Lucia Section (Phase III), Gerona, Tarlac is a DPWH-tracked public work in TARLAC, Region III. Reported contract value: ₱13,967,566.61. Status: Reported complete (DPWH). Contractor on record: ARCONIC INC. Figures trace to sumbong.

TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures along Tarlac River Control Left Dike, Sembrano-Sta. Lucia Section (Phase III), Gerona, Tarlac
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0005351

₱30,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0008977

₱13,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013807

₱11,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014075

₱70,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-21-0000627

₱50,553.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-21-0000969

₱21,582.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-21-0000970

₱2,192.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-21-0000626

₱540,204.00 · FY2021

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱13,967,566.61

Progress

Reported complete (DPWH)

Start Date

March 28, 2022

Target End

July 24, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.