Roads18N00103

REHABILITATION OF SAN LUIS - BINICALAN ROAD, SAN LUIS AGUSAN DEL SUR - PHASE 4, SAN LUIS, AGUSAN DEL SUR

REHABILITATION OF SAN LUIS - BINICALAN ROAD, SAN LUIS AGUSAN DEL SUR - PHASE 4, SAN LUIS, AGUSAN DEL SUR is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱142,577,082.22. Status: Reported complete (DPWH). Contractor on record: PREMIUM MEGASTRUCTURES INC. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱142,577,082.22

Progress

Reported complete (DPWH)

Start Date

October 25, 2018

Target End

May 18, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.