Buildings and Facilities16AB0096

CONST. OF ONE (1) STOREY - TWO (2) CL BLDG. NUEVA ERA CENTRAL E/S, NUEVA ERA, ILOCOS NORTE

CONST. OF ONE (1) STOREY - TWO (2) CL BLDG. NUEVA ERA CENTRAL E/S, NUEVA ERA, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 2nd DEO, Region I. Reported contract value: ₱1,913,778.58. Status: Reported complete (DPWH). Contractor on record: JLP CONST. Figures trace to dpwh.

Ilocos Norte 2nd DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Damaged Flood Control Facilities/Structures under the Laoag River Basin Flood Control and Sabo Project (LRBDCSP) Nueva Era Flood Control, Dong dong River, Brgy. Acnam, Nueva Era, Ilocos Norte
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-16-0038832

₱3,395,952.00 · FY2016

Released to Central Off (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

270 projects · ₱3.4B total · 0 flags

4. Implementation

Contract Amount

₱1,913,778.58

Progress

Reported complete (DPWH)

Start Date

August 2, 2016

Target End

November 24, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.