GAA 2025 SSP25NH0060

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY PAYASAN, LIANGA, SURIGAO DEL SUR

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY PAYASAN, LIANGA, SURIGAO DEL SUR is a DPWH-tracked public work in Surigao del Sur 1st DEO, Region XIII. Reported contract value: ₱38,593,617.00. Status: Past target date (DPWH On-Going). Contractor on record: CM TAN CONST. Figures trace to dpwh.

Surigao del Sur 1st DEO, Region XIII
Region: Region XIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 97%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Payasan, Lianga, Surigao del Sur
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Surigao del Sur 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱38,593,617.00

Progress

Past target date (DPWH On-Going)

Start Date

April 10, 2025

Target End

February 28, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.