Roads16AD0019

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT AND MANAGEMENT -4 (HDM-4) SALCEDO-DEL PILAR ROAD, K0361+2774-K0361+3834

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT AND MANAGEMENT -4 (HDM-4) SALCEDO-DEL PILAR ROAD, K0361+2774-K0361+3834 is a DPWH-tracked public work in Ilocos Sur 2nd DEO, Region I. Reported contract value: ₱28,124,954.83. Status: Reported complete (DPWH). Contractor on record: FIRST NORTHWAY DEVELOPMENT. Figures trace to dpwh.

Ilocos Sur 2nd DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures and Drainage System - Bucong Flood Control, Candon City, Ilocos Sur 2nd LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-16-0026232

₱75,905.00 · FY2016

Released to Alaminos National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

275 projects · ₱5.2B total · 0 flags

4. Implementation

Contract Amount

₱28,124,954.83

Progress

Reported complete (DPWH)

Start Date

March 23, 2016

Target End

November 16, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.