Roads23E00067

NETWORK DEVELOPMENT PROGRAM- CONST. OF MISSING LINKS/NEW ROADS- SOFRONIO ESPANOLA-QUEZON CROSS COUNTRY ROAD (PULOT INTERIOR-TAGUSAO SECTION), PACKAGE G, STA. 177+900-STA. 179+440; STA. 179+600-STA. 180+168, QUEZON, PALAWAN

NETWORK DEVELOPMENT PROGRAM- CONST. OF MISSING LINKS/NEW ROADS- SOFRONIO ESPANOLA-QUEZON CROSS COUNTRY ROAD (PULOT INTERIOR-TAGUSAO SECTION), PACKAGE G, STA. 177+900-STA. 179+440; STA. 179+600-STA. 180+168, QUEZON, PALAWAN is a DPWH-tracked public work in Region IV-B, Region IV-B. Reported contract value: ₱144,746,648.37. Status: Past target date (DPWH On-Going). Contractor on record: IVY MICHELLE CONST AND TRADING INC FORMERLY:IVY MICHELLE TRADING. Figures trace to dpwh.

Region IV-B, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

150 projects · ₱12.2B total · 0 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD, BATARAZA-RIZAL CROSS COUNTRY (SUMBILING-CANIPAAN), PACKAGE B, PALAWA

Region IV-B, Region IV-B

2023₱282.6M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)- CONST. OF SANDOVAL-PAJO-(IGANG-IGANG)-SARONG-OCAYAN ROAD, PACKAGE B, STA. 3+391.16-STA. 6+097.16, BATAR

Region IV-B, Region IV-B

2025₱279.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- CONST. OF SANDOVAL-PAJO-(IGANG-IGANG)-SARONG-OCAYAN ROAD PACKAGE C, STA. 6+097.16-STA. 9+297.66, BATARAZA, PALAWAN

Region IV-B, Region IV-B

2025₱279.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)- CONST. OF SANDOVAL-PAJO-(IGANG-IGANG)-SARONG-OCAYAN ROAD PACKAGE A, STA. 0+000.00-STA. 3+391.16, BATA

Region IV-B, Region IV-B

2025₱279.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)- CONST. OF PANAS-TAGBITA DIVERSION ROAD PACKAGE B, STA. 0+000.00-STA. 2+585.00, BATARAZA, PALAWAN

Region IV-B, Region IV-B

2025₱279.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)- CONST. OF PANAS-TAGBITA DIVERSION ROAD, PACKAGE A, STA. 0+000-STA. 2+820, BATARAZA, PALAWAN

Region IV-B, Region IV-B

2025₱279.3M
Past target date (DPWH On-Going)
View all 150 projects →

4. Implementation

Contract Amount

₱144,746,648.37

Progress

Past target date (DPWH On-Going)

Start Date

February 11, 2023

Target End

April 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.