Flood Control and Drainage17DL0049

B. MFO 2 - FLOOD MANAGEMENT SERVICES 1. CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS D. CONSTRUCTION/REHABILITATION OF FLOOD CONTROL STRUCTURES, SILANG RIVER, LOPEZ, QUEZON 4TH LD

B. MFO 2 - FLOOD MANAGEMENT SERVICES 1. CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS D. CONSTRUCTION/REHABILITATION OF FLOOD CONTROL STRUCTURES, SILANG RIVER, LOPEZ, QUEZON 4TH LD is a DPWH-tracked public work in Quezon 4th DEO, Region IV-A. Reported contract value: ₱18,812,337.04. Status: Reported complete (DPWH). Contractor on record: SYNDTITE CONST CORP FORMERLY: R C TAGALA CONST. Figures trace to dpwh.

Quezon 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation of Flood Control Structures, Silang River, Lopez, Quezon
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0021010

₱300,000,000.00 · FY2017

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

466 projects · ₱13.0B total · 1 flags

Other projects by this contractor

View all 466 projects →

4. Implementation

Contract Amount

₱18,812,337.04

Progress

Reported complete (DPWH)

Start Date

February 3, 2017

Target End

August 31, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.