GAA 2025 SSP25MI0016

INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (GUARDRAILS, PAVEMENT MARKINGS, ROAD SIGNS) ALONG BUKIDNON-COTABATO RD - K1642+(-177) - K1643+334, K1642+(-334) - K1642+(-177), K1642+(-468) - K1643+(-334), K1642+(-660) - K1642+(-468), K1643+334 - K1655+

INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (GUARDRAILS, PAVEMENT MARKINGS, ROAD SIGNS) ALONG BUKIDNON-COTABATO RD - K1642+(-177) - K1643+334, K1642+(-334) - K1642+(-177), K1642+(-468) - K1643+(-334), K1642+(-660) - K1642+(-468), K1643+334 - K1655+ is a DPWH-tracked public work in Cotabato 3rd DEO, Region XII. Reported contract value: ₱36,207,396.24. Status: Reported complete (DPWH). Contractor on record: P L SEBASTIAN CONST INC FORMERLY: P L SEBASTIAN CONST. Figures trace to dpwh.

Cotabato 3rd DEO, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱33,150,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Tinanan River, Package 4, Barangay Malibatuan, Arakan, Cotabato
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cotabato 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱36,207,396.24

Progress

Reported complete (DPWH)

Start Date

May 23, 2025

Target End

September 16, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.