Flood Control and Drainage19FG0036

REHABILITATION/IMPROVEMENT OF BICOL RIVER DOWNSTREAM OF STO. DOMINGO BRIDGE, NABUA, CAMARINES SURNABUA, CAMARINES SUR

REHABILITATION/IMPROVEMENT OF BICOL RIVER DOWNSTREAM OF STO. DOMINGO BRIDGE, NABUA, CAMARINES SURNABUA, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 5th DEO, Region V. Reported contract value: ₱27,920,211.88. Status: Reported complete (DPWH). Contractor on record: VIRGO CONST. Figures trace to dpwh.

Camarines Sur 5th DEO, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-19-0018815

₱0.00 · FY2019

Released to Division of Camarines Norte (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

57 projects · ₱405.6M total · 0 flags

4. Implementation

Contract Amount

₱27,920,211.88

Progress

Reported complete (DPWH)

Start Date

June 18, 2019

Target End

December 11, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.