GAA 2024 SSP24N00004

REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS ALONG DAANG MAHARLIKA (AGUSAN-DAVAO SECT)- K1241+(-321)- K1241+510, K1242+025- K1243+800

REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS ALONG DAANG MAHARLIKA (AGUSAN-DAVAO SECT)- K1241+(-321)- K1241+510, K1242+025- K1243+800 is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱163,606,213.92. Status: Past target date (DPWH On-Going). Contractor on record: EQUI-PARCO CONST CO. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱163,606,213.92

Progress

Past target date (DPWH On-Going)

Start Date

June 7, 2024

Target End

November 3, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.