Water Provision and Storage25IB0108

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM 1. MUNICIPAL BUILDING, BARANGAY 03, SALCEDO, EASTERN SAMAR 2. EVACUATION CENTER, BRGY. NAPARAAN, SALCEDO, EASTERN SAMAR 3. MUNICIPAL BUILDING, BRGY. 4, JIPAPAD, EA

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM 1. MUNICIPAL BUILDING, BARANGAY 03, SALCEDO, EASTERN SAMAR 2. EVACUATION CENTER, BRGY. NAPARAAN, SALCEDO, EASTERN SAMAR 3. MUNICIPAL BUILDING, BRGY. 4, JIPAPAD, EA is a DPWH-tracked public work in Eastern Samar DEO, Region VIII. Reported contract value: ₱2,599,795.19. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: RYJEN CONST 51781. Figures trace to dpwh.

Eastern Samar DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Guibuangan, Can-Avid, Eastern Samar
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Eastern Samar DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,599,795.19

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

July 14, 2025

Target End

October 6, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.