Buildings and Facilities23I00167

CONSTRUCTION OF 2-STOREY 4-CLASSROOM SCHOOL BUILDING, PINAMUDLAN ELEMENTARY SCHOOL, SAN FRANCISCO, SOUTHERN LEYTE

CONSTRUCTION OF 2-STOREY 4-CLASSROOM SCHOOL BUILDING, PINAMUDLAN ELEMENTARY SCHOOL, SAN FRANCISCO, SOUTHERN LEYTE is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱9,998,058.86. Status: Past target date (DPWH On-Going). Contractor on record: RYJEN CONST. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱9,984,154 · RYJEN CONSTRUCTION

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    98% reported · imagery 2014-06-16 → 2024-06-04

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF 2-STOREY 4-CLASSROOM SCHOOL BUILDING, PINAMUDLAN ELEMENTARY SCHOOL, SAN FRANCISCO, SOUTHERN LEYTE

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

Confirmed (exact contract ID) · 100%

CID No. 23I00167

₱9,984,154.19 · RYJEN CONSTRUCTION

Award / contract ref: CID No. 23I00167

Contractor

D

19 projects · ₱142.6M total · 0 flags

4. Implementation

Contract Amount

₱9,998,058.86

Progress

Past target date (DPWH On-Going)

Start Date

December 6, 2023

Target End

September 26, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VIII (Eastern Visayas)Southern LeyteSan FranciscoPinamudlan
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Storm surgeDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.