Roads20C00015

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, NUEVA ECIJA-AURORA ROAD, PROVINCE OF NUEVA ECIJA

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, NUEVA ECIJA-AURORA ROAD, PROVINCE OF NUEVA ECIJA is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱144,749,799.72. Status: Reported complete (DPWH). Contractor on record: NEWBIG FOUR J CONST INC FORMERLY: FOUR J CONST. Figures trace to dpwh.

Region III, Region III
Region: Region III

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱144,749,799.72

Progress

Reported complete (DPWH)

Start Date

December 13, 2020

Target End

August 9, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.