GAA 2025 DA FMR25DJ0139

CONCRETING OF BRGY. MANGGALANG TULO-TULO FMR, BRGY. MANGGALANG TULO-TULO, SARIAYA, QUEZON

CONCRETING OF BRGY. MANGGALANG TULO-TULO FMR, BRGY. MANGGALANG TULO-TULO, SARIAYA, QUEZON is a DPWH-tracked public work in Quezon 2nd DEO, Region IV-A. Reported contract value: ₱14,477,250.41. Status: Past target date (DPWH On-Going). Contractor on record: WAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS. Figures trace to dpwh.

Quezon 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Drainage Structure, Barangay 10, Lucena City, Quezon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Quezon 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱14,477,250.41

Progress

Past target date (DPWH On-Going)

Start Date

August 18, 2025

Target End

March 30, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.