Roads20A00058

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS-MANILA NORTH ROAD - K0266+800 - K0267+275

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS-MANILA NORTH ROAD - K0266+800 - K0267+275 is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱14,689,214.56. Status: Reported complete (DPWH). Contractor on record: DJCM CONST CORP FORMERLY: DJCM CONST. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

127 projects · ₱2.5B total · 4 flags

4. Implementation

Contract Amount

₱14,689,214.56

Progress

Reported complete (DPWH)

Start Date

February 19, 2020

Target End

November 25, 2020