Flood Control and Drainage16FB0065

CONSTRUCTION OF FLOOD CONTROL SYSTEM ALONG YAWA RIVER, 2ND DISTRICT, BRGY. BOGTONG, LEGASPI CITY, ALBAY, 2ND LD

CONSTRUCTION OF FLOOD CONTROL SYSTEM ALONG YAWA RIVER, 2ND DISTRICT, BRGY. BOGTONG, LEGASPI CITY, ALBAY, 2ND LD is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱27,911,228.49. Status: Reported complete (DPWH). Contractor on record: SUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System along Yawa River, 2nd District, Brgy. Bogtong, Legaspi City, Albay, 2nd LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Agency-level releases for FY2016, not tied to this contract

Albay 2nd DEO · SARO 2,111 (₱111,347,307,043.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP- MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF CRUISE PORT AND FACILITIES PACKAGE 3, LEGAZPI CITY, LEGAZPI CITY, ALBAY (2ND LEGISLATIVE DISTRICT

Region V, Region V

2024₱391.8M
Past target date (DPWH On-Going)
No sat.

SIPAG - COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES - CONSTRUCTION OF CAUSEWAY, SECTION 3.14A, TACLOBAN CITY, LEYTE

Region VIII, Region VIII

2025₱313.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION-CONSTRUCTION OF COASTAL ROAD, BARANGAY POBLACION, RAPU-RAPU, ALBAY, RAPU-RAPU, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱292.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, BARANGAY MOROCBOROCAN TO BARANGAY POBLACION, R

Region V, Region V

2024₱291.1M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIP[AG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, BRGY. INARAWAN, PHASE I, NAUJAN, ORIENTAL MINDORO

Region IV-B, Region IV-B

2024₱279.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, MAGALLANG-MOROPONROS, LIBON/OAS, ALBAY (PHASE

Region V, Region V

2024₱244.8M
Past target date (DPWH On-Going)
View all 107 projects →

4. Implementation

Contract Amount

₱27,911,228.49

Progress

Reported complete (DPWH)

Start Date

July 28, 2016

Target End

December 25, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.