Roads21CJ0065

CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS CONSTRUCTION OF ROAD, MABABANABA, SAN JOSE TO STA. INES WEST, STA. IGNACIA VIA PANSIGUAN, BARANGAY MABABANABA, MUNICIPALITY OF SAN JOSE TO BARANGAY STA

CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS CONSTRUCTION OF ROAD, MABABANABA, SAN JOSE TO STA. INES WEST, STA. IGNACIA VIA PANSIGUAN, BARANGAY MABABANABA, MUNICIPALITY OF SAN JOSE TO BARANGAY STA is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱80,384,498.55. Status: Reported complete (DPWH). Contractor on record: ROYAL CROWN MONARCH CONST. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱43,516,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures Along Moriones River Right Bank Including Road Component, Balanti Section (Phase V), Sta. 0+000 - Sta. 0+421, Balanti, Tarlac City, Tarlac
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Tarlac DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

328 projects · ₱20.7B total · 0 flags

4. Implementation

Contract Amount

₱80,384,498.55

Progress

Reported complete (DPWH)

Start Date

March 29, 2021

Target End

January 4, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.