Roads24F00022

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, SITIO BUSAY, BARANGAY CARUHAYON TO SITIO BAYBA

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, SITIO BUSAY, BARANGAY CARUHAYON TO SITIO BAYBA is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱24,749,798.58. Status: Past target date (DPWH On-Going). Contractor on record: FULLEROS BOTOX BUILDERS AND DESIGN. Figures trace to dpwh.

Region V, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

Possible match · 75%

CW24-05-005

₱41,186,029.81 · FULLEROS BOTOX BUILDERS AND DESIGN

Contractor

C

23 projects · ₱542.5M total · 0 flags

4. Implementation

Contract Amount

₱24,749,798.58

Progress

Past target date (DPWH On-Going)

Start Date

August 21, 2024

Target End

June 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.