Construction of Flood Mitigation Structure21KG0030

Construction of Revetment/ Riverbank Protection along Maranding River Stream, Barangay Maranding Annex, Kapatagan, Lanao del Norte

Construction of Revetment/ Riverbank Protection along Maranding River Stream, Barangay Maranding Annex, Kapatagan, Lanao del Norte is a DPWH-tracked public work in LANAO DEL NORTE, Region X. Reported contract value: ₱32,884,498.68. Status: Reported complete (DPWH). Contractor on record: LANAO BUILDER AND ENT. Figures trace to sumbong.

LANAO DEL NORTE, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱11,550,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Brgy. Pendolunan, Munai, Lanao del Norte
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0011477

₱57,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014194

₱10,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010194

₱7,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROX-21-0008695

₱6,701,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007581

₱161,306,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROX-21-0008070

₱302,860.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROX-21-0010472

₱184,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROX-21-0010473

₱20,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROX-21-0008696

₱628,000.00 · FY2021

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱32,884,498.68

Progress

Reported complete (DPWH)

Start Date

April 13, 2022

Target End

January 13, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.