Buildings and Facilities17OF0165

CONSTRUCTION OF FOUR (4) STOREY TWENTY(20) CLASSROOM SCHOOL BUILDING AT BAGONG PAG-ASA E/S, Q.C.

CONSTRUCTION OF FOUR (4) STOREY TWENTY(20) CLASSROOM SCHOOL BUILDING AT BAGONG PAG-ASA E/S, Q.C. is a DPWH-tracked public work in Quezon City 1st DEO, National Capital Region. Reported contract value: ₱44,899,328.90. Status: Reported complete (DPWH). Contractor on record: AYLAN CONST. Figures trace to dpwh.

Quezon City 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Floodgate along Talayan Creek, Quezon City
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0021010

₱300,000,000.00 · FY2017

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱44,899,328.90

Progress

Reported complete (DPWH)

Start Date

December 13, 2017

Target End

August 4, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.