Roads17J00179

WIDENING OF BRIDGE APPROACH AND CAUSEWAY IMPROVEMENT OF BRIDGE APPROACH CAUSEWAY ALONG NATIONAL ROAD, SIMUNUL CIRCUMFERENTIAL NATIONAL ROAD, TAWI TAWI, STA. 15+200 TO STA. 15+331.00, NET LENGTH: 131.00 LN.M.

WIDENING OF BRIDGE APPROACH AND CAUSEWAY IMPROVEMENT OF BRIDGE APPROACH CAUSEWAY ALONG NATIONAL ROAD, SIMUNUL CIRCUMFERENTIAL NATIONAL ROAD, TAWI TAWI, STA. 15+200 TO STA. 15+331.00, NET LENGTH: 131.00 LN.M. is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱27,930,335.60. Status: Reported complete (DPWH). Contractor on record: FFJJ CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱27,930,335.60

Progress

Reported complete (DPWH)

Start Date

February 20, 2018

Target End

October 17, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.