GAA 2025 SSP25II0033

CONSTRUCTION OF ROAD, BRGY. VIGO TO BRGY. ATIPOLO, LAOANG, NORTHERN SAMAR, NORTHERN SAMAR 2ND DISTYRICT

CONSTRUCTION OF ROAD, BRGY. VIGO TO BRGY. ATIPOLO, LAOANG, NORTHERN SAMAR, NORTHERN SAMAR 2ND DISTYRICT is a DPWH-tracked public work in Northern Samar 2nd DEO, Region VIII. Reported contract value: ₱19,569,800.00. Status: Past target date (DPWH On-Going). Contractor on record: CDU CONST. Figures trace to dpwh.

Northern Samar 2nd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Gamay Flood Control Structure and Drainage System, Gamay River Basin, Gamay, Northern Samar
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Northern Samar 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

343 projects · ₱9.6B total · 7 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0861+453 - K0862+355, K0862+380 - K0862+786, K0863+064 - K0863+364, K0863+600 - K0863+685, K0863+685 -

Region VIII, Region VIII

2025₱151.5M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR) - K0734+578 - K0735+526, K0742+826 - K0745+000, SAMAR 1ST LD

Region VIII, Region VIII

2024₱147.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MAROYONDOYON CREEK & KAGLANGKOY CREEK, CATARMAN, NORTHERN SAMAR

Northern Samar 1st DEO, Region VIII

2025₱144.7M
Past target date (DPWH On-Going)
No sat.

VIILP - LOCAL ROADS AND BRIDGES - LOCAL ROADS - ROAD OPENING / CONCRETING OF HINANGUTDAN, STA. RITA TO SAN ROQUE, VILLAREAL, SAMAR (PHASE I)

Region VIII, Region VIII

2020₱136.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM- (KATUPARAN)- ITBAYAT AIRPORT /NIA CIRCUMFERENTIAL ROAD, ITBAYAT, BATANES

Region II, Region II

2022₱106.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - ROAD OPENING/CONCRETING OF HINANGUTDAN - STA. RITA TO SAN ROQUE - VILLAREAL, SAMAR (PHASE III), SAMAR 2ND LD

Region VIII, Region VIII

2021₱99.4M
Reported complete (DPWH)
View all 343 projects →

4. Implementation

Contract Amount

₱19,569,800.00

Progress

Past target date (DPWH On-Going)

Start Date

April 7, 2025

Target End

October 3, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.