Roads22JG0048

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ALONG NRJ BOGAYO-KITAAN DAGAT-SUMINALOM RD, KUMALARANG, ZAMBOANGA DEL SUR

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ALONG NRJ BOGAYO-KITAAN DAGAT-SUMINALOM RD, KUMALARANG, ZAMBOANGA DEL SUR is a DPWH-tracked public work in Zamboanga del Sur 2nd DEO, Region IX. Reported contract value: ₱30,419,615.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: PYRAMID CONSOLIDATED BUILDERS. Figures trace to dpwh.

Zamboanga del Sur 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱40,621,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Left Bank of Dohinob River (Upstream and Downstream), San Antonio, Manukan, Zamboanga del Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Zamboanga del Sur 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱30,419,615.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 31, 2022

Target End

September 1, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.