Buildings and Facilities16PJ0036

BASIC EDUCATIONAL FACILITIES FUND (BEFF - BATCH 7) CONSTRUCTION OF SENIOR HIGH SCHOOL CLASSROOMS - STA. MARIA NHS - 2STY8CL, STA. MARIA, ALFONSO LISTA (POTIA), IFUGAO

BASIC EDUCATIONAL FACILITIES FUND (BEFF - BATCH 7) CONSTRUCTION OF SENIOR HIGH SCHOOL CLASSROOMS - STA. MARIA NHS - 2STY8CL, STA. MARIA, ALFONSO LISTA (POTIA), IFUGAO is a DPWH-tracked public work in Ifugao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱11,164,846.93. Status: Reported complete (DPWH). Contractor on record: C R DOMINGO CONST AND POWER DEVELOPMENT INC FOR C R DOMINGO CONST INC. Figures trace to dpwh.

Ifugao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-16-0038385

₱343,000.00 · FY2016

Released to Binagbag High School - Diosdado Macapagal Hig Fund (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

87 projects · ₱3.2B total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS, ROMAN EXPRESSWAY, PROVINCE OF BATAAN

Region III, Region III

2019₱131.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF QUIMALABASA NORTE FLOOD CONTROL STRUCTURE SECTION 5,

Isabela 4th DEO, Region II

2025₱106.1M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - SANTIAGO CIRCUMFERENTIAL ROAD, ISABELA

Region II, Region II

2021₱104.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CAUAYAN CITY BY-PASS ROAD, PACKAGE 1, ISABELA; STA. 000+000-STA. 001+085

Region II, Region II

2020₱103.1M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT: ROAD WIDENING-PRIMARY ROADS-DAANG MAHARLIKA (LZ), CORDON AND SANTIAGO, ISABELA

Region II, Region II

2020₱99.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES: VILLA GAMIAO, SAN ANTONIO, DARAMUANGAN SUR AND SALINUNGAN EAST ROADS CONNECTING TO MUNGGO PROCESSING AND PACKAGING CENTER

Region II, Region II

2021₱97.8M
Reported complete (DPWH)
View all 87 projects →

4. Implementation

Contract Amount

₱11,164,846.93

Progress

Reported complete (DPWH)

Start Date

October 2, 2016

Target End

February 28, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.