CONSTRUCTION OF A SOLAR-POWERED WATER SYSTEM IN BRGY. NEW JANIUAY, MLANG, COTABATO

CONSTRUCTION OF A SOLAR-POWERED WATER SYSTEM IN BRGY. NEW JANIUAY, MLANG, COTABATO is a DPWH-tracked public work in Cotabato 3rd DEO, Region XII. Reported contract value: ₱4,818,319.97. Status: Reported complete (DPWH). Contractor on record: JOHN RAY DEVELOPER AND SUPPLIES. Figures trace to dpwh.

Cotabato 3rd DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱41,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Kabacan River Flood Control Project (Plang to Pulangi River Section-Phase IV), USM, Kabacan, North Cotabato
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cotabato 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

Probable match · 94%

construction project

₱5,065,784.06 · JOHN RAY DEVELOPER AND SUPPLIES

Probable match · 85%

Cluster 15 CY 2017 BEFF Repair of Classrooms

₱4,175,899.49 · JOHN RAY DEVELOPER AND SUPPLIES

4. Implementation

Contract Amount

₱4,818,319.97

Progress

Reported complete (DPWH)

Start Date

January 3, 2024

Target End

April 1, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.