Water Provision and Storage23JI0033

CONSTRUCTION OF WATER SYSTEM, BARANGAY BATERIA, OLUTANGA, ZAMBOANGA SIBUGAY

CONSTRUCTION OF WATER SYSTEM, BARANGAY BATERIA, OLUTANGA, ZAMBOANGA SIBUGAY is a DPWH-tracked public work in Zamboanga Sibugay 1st DEO, Region IX. Reported contract value: ₱4,949,228.96. Status: Reported complete (DPWH). Contractor on record: JGC CONSTRUCTION. Figures trace to dpwh.

Zamboanga Sibugay 1st DEO, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Sibuguey River, Barangay Villacastor, Buug, Zamboanga Sibugay Package 3
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Zamboanga Sibugay 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,949,228.96

Progress

Reported complete (DPWH)

Start Date

February 6, 2023

Target End

August 4, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.