Flood Control and Drainage21FB0119

LIP-FLOOD CONTROL AND DRAINAGE: CONSTRUCTION OF RIVER BANK PROTECTION WORKS AND DRAINAGE SYSTEM ALONG BARANGAY TAMAOYAN, LEGAZPI CITY

LIP-FLOOD CONTROL AND DRAINAGE: CONSTRUCTION OF RIVER BANK PROTECTION WORKS AND DRAINAGE SYSTEM ALONG BARANGAY TAMAOYAN, LEGAZPI CITY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱49,498,230.66. Status: Reported complete (DPWH). Contractor on record: PROTECH CONST & DEVELOPMENT CORP FORMERLY. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Dike and Bank Protection Works along Arimbay-Matanag River, Legazpi City, Albay
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Albay 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

25 projects · ₱1.6B total · 0 flags

4. Implementation

Contract Amount

₱49,498,230.66

Progress

Reported complete (DPWH)

Start Date

March 15, 2021

Target End

September 10, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.