Roads24FO0046

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LIGAO-PIO DURAN RD - K0527 + 100 - K0527 + 150

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LIGAO-PIO DURAN RD - K0527 + 100 - K0527 + 150 is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱7,809,606.81. Status: Reported complete (DPWH). Contractor on record: SULVIR ENGINEERING AND CONST. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tobgon Flood Mitigation Structure, Ligao City, Albay
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Albay 3rd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱7,809,606.81

Progress

Reported complete (DPWH)

Start Date

April 2, 2024

Target End

August 29, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.