Flood Control and Drainage24E00170

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF KALITAWAN RIVER FLOOD CONTROL STRUCTURE, STA. 000+700-STA. 000+860; STA. 000+920-STA. 001+040 (LS),

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF KALITAWAN RIVER FLOOD CONTROL STRUCTURE, STA. 000+700-STA. 000+860; STA. 000+920-STA. 001+040 (LS), is a DPWH-tracked public work in Region IV-B, Region IV-B. Reported contract value: ₱192,998,347.20. Status: Past target date (DPWH On-Going). Contractor on record: IVY MICHELLE CONST AND TRADING INC FORMERLY:IVY MICHELLE TRADING. Figures trace to dpwh.

Region IV-B, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD, BATARAZA-RIZAL CROSS COUNTRY (SUMBILING-CANIPAAN), PACKAGE B, PALAWA

Region IV-B, Region IV-B

2023₱282.6M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)- CONST. OF SANDOVAL-PAJO-(IGANG-IGANG)-SARONG-OCAYAN ROAD, PACKAGE B, STA. 3+391.16-STA. 6+097.16, BATAR

Region IV-B, Region IV-B

2025₱279.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- CONST. OF SANDOVAL-PAJO-(IGANG-IGANG)-SARONG-OCAYAN ROAD PACKAGE C, STA. 6+097.16-STA. 9+297.66, BATARAZA, PALAWAN

Region IV-B, Region IV-B

2025₱279.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)- CONST. OF SANDOVAL-PAJO-(IGANG-IGANG)-SARONG-OCAYAN ROAD PACKAGE A, STA. 0+000.00-STA. 3+391.16, BATA

Region IV-B, Region IV-B

2025₱279.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)- CONST. OF PANAS-TAGBITA DIVERSION ROAD PACKAGE B, STA. 0+000.00-STA. 2+585.00, BATARAZA, PALAWAN

Region IV-B, Region IV-B

2025₱279.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)- CONST. OF PANAS-TAGBITA DIVERSION ROAD, PACKAGE A, STA. 0+000-STA. 2+820, BATARAZA, PALAWAN

Region IV-B, Region IV-B

2025₱279.3M
Past target date (DPWH On-Going)
View all 150 projects →

4. Implementation

Contract Amount

₱192,998,347.20

Progress

Past target date (DPWH On-Going)

Start Date

March 9, 2024

Target End

July 1, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.