Buildings and Facilities17DK0152

CONSTRUCTION OF TWO(2) UNITS ONE(1) STOREY WORKSHOP BUILDING (SCIENCE LABORATORY) @ BUSDAK NATIONAL HIGH SCHOOL, FORMERLY BUSDAK NATIONAL HIGH SCHOOL, PATNAUNGAN NATIONAL HIGH SCHOOL ANNEX, PATNANUNGAN, QUEZON

CONSTRUCTION OF TWO(2) UNITS ONE(1) STOREY WORKSHOP BUILDING (SCIENCE LABORATORY) @ BUSDAK NATIONAL HIGH SCHOOL, FORMERLY BUSDAK NATIONAL HIGH SCHOOL, PATNAUNGAN NATIONAL HIGH SCHOOL ANNEX, PATNANUNGAN, QUEZON is a DPWH-tracked public work in Quezon 1st DEO, Region IV-A. Reported contract value: ₱7,488,370.00. Status: Reported complete (DPWH). Contractor on record: E A AYALA CONST AND SUPPLY. Figures trace to dpwh.

Quezon 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Barangay Aliliw, Lucban, Quezon
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0021010

₱300,000,000.00 · FY2017

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱7,488,370.00

Progress

Reported complete (DPWH)

Start Date

November 22, 2017

Target End

May 15, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.