Water Provision and Storage20ME0105

CONSTRUCTION OF WATER SYSTEM-PATAG (BRGY. PROPER);

CONSTRUCTION OF WATER SYSTEM-PATAG (BRGY. PROPER); is a DPWH-tracked public work in Sarangani DEO, Region XII. Reported contract value: ₱1,973,527.91. Status: Reported complete (DPWH). Contractor on record: TANGCA CONST CORP. Figures trace to dpwh.

Sarangani DEO, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bagacay Bridge Flood Control, Alabel, Sarangani
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Sarangani DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

13 projects · ₱56.7M total · 0 flags

4. Implementation

Contract Amount

₱1,973,527.91

Progress

Reported complete (DPWH)

Start Date

September 13, 2020

Target End

January 10, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.