CONST. OF 2STY 1CL. SCI. LAB. & ICT ICT LAB. SUMBILING NATIONAL HIGH SCHOOL, BATARAZA, PALAWAN

CONST. OF 2STY 1CL. SCI. LAB. & ICT ICT LAB. SUMBILING NATIONAL HIGH SCHOOL, BATARAZA, PALAWAN is a DPWH-tracked public work in Palawan 2nd DEO, Region IV-B. Reported contract value: ₱9,441,453.77. Status: Reported complete (DPWH). Contractor on record: SYNDTITE CONST CORP FORMERLY: R C TAGALA CONST. Figures trace to dpwh.

Palawan 2nd DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Inogbong Flood Control Structure, Bataraza, Palawan
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-18-0005523

₱0.00 · FY2018

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

466 projects · ₱13.0B total · 1 flags

Other projects by this contractor

View all 466 projects →

4. Implementation

Contract Amount

₱9,441,453.77

Progress

Reported complete (DPWH)

Start Date

September 5, 2018

Target End

April 2, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.