Roads24K00425

CONSTRUCTION OF CAUSEWAY INCLUDING FACILITIES (PHASE 1), BARANGAY POBLACION, KOLAMBUGAN, LANAO DEL NORTE

CONSTRUCTION OF CAUSEWAY INCLUDING FACILITIES (PHASE 1), BARANGAY POBLACION, KOLAMBUGAN, LANAO DEL NORTE is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱95,464,354.31. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: LANAO BUILDER AND ENT. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱95,464,354.31

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

September 26, 2024

Target End

June 7, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.