Flood Control and Drainage16OI0106

CONST. OF SLOPE PROTECTION AT& OTHER IMPV'T AT TALON CREEK (FROM CAA BRIDGE TO TALON BRIDGE), LAS PI

CONST. OF SLOPE PROTECTION AT& OTHER IMPV'T AT TALON CREEK (FROM CAA BRIDGE TO TALON BRIDGE), LAS PI is a DPWH-tracked public work in Las Piñas-Muntinlupa DEO, National Capital Region. Reported contract value: ₱62,916,561.42. Status: Reported complete (DPWH). Contractor on record: I&E CONST CORP FORMERLY: I&E CONSTR. Figures trace to dpwh.

Las Piñas-Muntinlupa DEO, National Capital Region
Region: National Capital Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱80,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Structures and Other Improvements Including Removal of Informal Settlers along Zapote River from Barangay Talon 5 to Barangay Almanza 2, Las Piñas City , Lone District
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-17-0020681

₱239,190.00 · FY2017

Released to Division of Tandag Re City (8 (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

165 projects · ₱10.9B total · 12 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF MISSING LINKS/ NEW ROADS GENERAL NAKAR - DINGALAN ROAD (GEN. NAKAR SIDE), PACKAGE A, QUEZON

Region IV-A, Region IV-A

2022₱289.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)IMUS-BACOOR LINK ROAD, PACKAGE 2, BACOOR, CAVITE

Region IV-A, Region IV-A

2025₱280.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)IMUS-BACOOR LINK ROAD, PACKAGE 1, BACOOR, CAVITE

Region IV-A, Region IV-A

2025₱280.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURES AND OTHER IMPROVEMENTS AT BARANGAYS TALON 1 TO TALON 3, LAS PINAS CITY

Las Piñas-Muntinlupa DEO, National Capital Region

2025₱218.3M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF BASUD-LANOT ROAD, BASUD,

Region V, Region V

2024₱187.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF DAET-SAN VICENTE-SAN LOR

Region V, Region V

2024₱183.3M
Past target date (DPWH On-Going)
View all 165 projects →

4. Implementation

Contract Amount

₱62,916,561.42

Progress

Reported complete (DPWH)

Start Date

March 20, 2017

Target End

February 12, 2018