Flood Control and Drainage23AA0156

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - REHABILITATION OF ERODED BANK REVETMENT WITH GABION FOOTING PROTECTION ALONG BALAOI RIVER REVETMENT, BARANGAY BALAOI, PAGUDPUD, ILOCOS NORTE

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - REHABILITATION OF ERODED BANK REVETMENT WITH GABION FOOTING PROTECTION ALONG BALAOI RIVER REVETMENT, BARANGAY BALAOI, PAGUDPUD, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱14,699,867.42. Status: Past target date (DPWH On-Going). Contractor on record: MEGAPOLITAN BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures along Laoag River Basin and tributaries, (Right Bank), Buttong Creek, Barangay Buttong, Laoag City, Ilocos Norte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Ilocos Norte 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

354 projects · ₱7.2B total · 6 flags

Other projects by this contractor

No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SRIP AND ITS APPURTENANT STRUCTURE, CABANGARAN SRIP, BARANGAY CABANGARAN, VINTAR, ILOCOS NORTE

Region I, Region I

2025₱149.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG QUIAOIT RIVER, DOWNSTREAM, PHASE 2, ALWINALDO BRIDGE, BARANGAY MAIPALIG, BATAC CITY, ILOCOS NORTE

Ilocos Norte 2nd DEO, Region I

2025₱141.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG QUIAOIT RIVER, DOWNSTREAM, PHASE 1, ALWINALDO BRIDGE, BARANGAY MAIPALIG, BATAC CITY, ILOCOS NORTE

Ilocos Norte 2nd DEO, Region I

2025₱141.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG QUIAOIT RIVER, BARANGAY MABALENG, BATAC CITY, ILOCOS NORTE

Region I, Region I

2024₱122.7M
Past target date (DPWH On-Going)

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF QUIAOIT RIVER DIVERSION CANAL, BATAC CITY, ILOCOS NORTE

Region I, Region I

2024₱115.8M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), CONSTRUCTION OF SWIP, BARANGAY CAMANDINGAN, CITY OF BATAC, ILOCOS NORTE

Region I, Region I

2025₱112.3M
Past target date (DPWH On-Going)
View all 354 projects →

4. Implementation

Contract Amount

₱14,699,867.42

Progress

Past target date (DPWH On-Going)

Start Date

April 20, 2023

Target End

November 11, 2023

5. Audit