Bridges24K00413

CONSTRUCTION OF BRIDGE INCLUDING APPROACHES, JCT. BUKIDNON DAVAO CITY ROAD-PALACAPAO-EAST DALURONG-WEST DALURONG-SINAYSAYAN ROAD (CROSSING RAWARI RIVER, WEST DALURONG-SINAYSAYAN SECTION), KITAOTAO, BUKIDNON (PACKAGE 2)

CONSTRUCTION OF BRIDGE INCLUDING APPROACHES, JCT. BUKIDNON DAVAO CITY ROAD-PALACAPAO-EAST DALURONG-WEST DALURONG-SINAYSAYAN ROAD (CROSSING RAWARI RIVER, WEST DALURONG-SINAYSAYAN SECTION), KITAOTAO, BUKIDNON (PACKAGE 2) is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱85,747,777.88. Status: Past target date (DPWH On-Going). Contractor on record: ULTICON BUILDERS INC. Figures trace to dpwh.

Region X, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱85,747,777.88

Progress

Past target date (DPWH On-Going)

Start Date

August 30, 2024

Target End

June 10, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.