Roads22CF0051

ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - CABANATUAN CITY - CARMEN RD - K0125+000-K0126+000

ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - CABANATUAN CITY - CARMEN RD - K0125+000-K0126+000 is a DPWH-tracked public work in Nueva Ecija 2nd DEO, Region III. Reported contract value: ₱15,516,494.74. Status: Reported complete (DPWH). Contractor on record: DGSARM BUILDERS INC FORMERLY: D G SARMENTA CONST. Figures trace to dpwh.

Nueva Ecija 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Pampanga River Flood Control, Barangay Tabuating, San Leonardo, Nueva Ecija
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Nueva Ecija 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

145 projects · ₱2.7B total · 5 flags

4. Implementation

Contract Amount

₱15,516,494.74

Progress

Reported complete (DPWH)

Start Date

April 8, 2022

Target End

December 25, 2022