Roads20J00045

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ROAD WIDENING ZAMBOANGA CITY DIVERSION ROAD, ZAMBOANGA CITY

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ROAD WIDENING ZAMBOANGA CITY DIVERSION ROAD, ZAMBOANGA CITY is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱126,518,058.75. Status: Reported complete (DPWH). Contractor on record: MIN CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

16 projects · ₱530.3M total · 0 flags

4. Implementation

Contract Amount

₱126,518,058.75

Progress

Reported complete (DPWH)

Start Date

February 21, 2020

Target End

November 12, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.