Roads16FM0016

OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, SAN FERNANDO NORTH ROAD, SAN JACINTO-MONREAL, MASBATE.

OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, SAN FERNANDO NORTH ROAD, SAN JACINTO-MONREAL, MASBATE. is a DPWH-tracked public work in Masbate 1st DEO, Region V. Reported contract value: ₱26,590,884.66. Status: Reported complete (DPWH). Contractor on record: VERZONTAL INFRASTRUCTURE CORP FORMERLY: VERZONTAL BUILDERS INC. Figures trace to dpwh.

Masbate 1st DEO, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-16-0038866

₱-40,907,545.00 · FY2016

Released to Northern Sa (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

84 projects · ₱2.0B total · 0 flags

4. Implementation

Contract Amount

₱26,590,884.66

Progress

Reported complete (DPWH)

Start Date

April 3, 2016

Target End

August 22, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.