Bridges23DI0101

REPLACEMENT OF PERMANENT WEAK BRIDGES - MAITIM BR. (B02510LZ) ALONG CALAMBA-STA CRUZ-FAMY JCT RD

REPLACEMENT OF PERMANENT WEAK BRIDGES - MAITIM BR. (B02510LZ) ALONG CALAMBA-STA CRUZ-FAMY JCT RD is a DPWH-tracked public work in Laguna 2nd DEO, Region IV-A. Reported contract value: ₱29,398,266.02. Status: Reported complete (DPWH). Contractor on record: R'CEL GEN CONTRACTOR. Figures trace to dpwh.

Laguna 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Malaban, Bi±an City, Laguna
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Laguna 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

115 projects · ₱1.7B total · 0 flags

4. Implementation

Contract Amount

₱29,398,266.02

Progress

Reported complete (DPWH)

Start Date

April 5, 2023

Target End

November 12, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.