Water Provision and Storage23PF0051

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM (RWCS) CY 2023 WITHIN DPWH-BENGUET SECOND DISTRICT ENGINEERING OFFICE

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM (RWCS) CY 2023 WITHIN DPWH-BENGUET SECOND DISTRICT ENGINEERING OFFICE is a DPWH-tracked public work in Benguet 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱2,311,578.00. Status: Reported complete (DPWH). Contractor on record: EFLER CONST AND ENT. Figures trace to dpwh.

Benguet 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

Confirmed (exact contract ID) · 100%

23PF0051Const./Rehabilitation of Water Supply

₱2,311,578.00 · EFLER CONSTRUCTION AND ENTERPRISE

Contractor

59 projects · ₱614.8M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF PROPER GADANG-LAO-ANGAN ROAD, KAPANGAN, BENGUET

Benguet 2nd DEO, Cordillera Administrative Region

2024₱95.3M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITHIN AGNO RIVER BASIN: ALONG AGNO RIVER LAPALAP SECTION, STA. 10+802 - STA. 11+162 (BS), BUGUIAS, BENGUET

Benguet 2nd DEO, Cordillera Administrative Region

2025₱41.1M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF 4 STOREY 8 CLASSROOM SCHOOL BUILDING, LAM-AYAN INTEGRATED SCHOOL, BUGUIAS, BENGUET

Benguet 2nd DEO, Cordillera Administrative Region

2024₱39.8M
Past target date (DPWH On-Going)
No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS: GOV. BADO DANGWA NATIONAL RD - K0291+570 - K0291+670, K0292+136 - K0292+290, K0292+445 - K0292+520

Benguet 2nd DEO, Cordillera Administrative Region

2025₱38.8M
Past target date (DPWH On-Going)
No sat.

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE: BAGUIO- BONTOC ROAD - K0266+600 - K0266+700, K0267+150 - K0267+180, K0268+850 - K0268+920, K0270+015 - K0270+045, K0272+713 - K0272+770, TUBLAY- ATOK, BENGUET

Benguet 2nd DEO, Cordillera Administrative Region

2023₱29.4M
Reported complete (DPWH)
No sat.

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS: BAGUIO-BONTOC RD - K0266+500-K0266+525, K0266+600-K0266+605, K0269+568-K0269+578, K0269+677-K0269+690, K0270+017-K0270+043, K0270+700-K0270+720, K0270+833-K0270+860, K0270+

Benguet 2nd DEO, Cordillera Administrative Region

2025₱27.2M
Past target date (DPWH On-Going)
View all 59 projects →

4. Implementation

Contract Amount

₱2,311,578.00

Progress

Reported complete (DPWH)

Start Date

July 12, 2023

Target End

August 7, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.