Flood Control and Drainage17FD0101

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BICOL RIVER, BRGY. BALIUAG VIEJO, MINALABAC, CAMARINES SUR

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BICOL RIVER, BRGY. BALIUAG VIEJO, MINALABAC, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 2nd DEO, Region V. Reported contract value: ₱97,000,000.00. Status: Reported complete (DPWH). Contractor on record: NEWBIG FOUR J CONST INC FORMERLY: FOUR J CONST. Figures trace to dpwh.

Camarines Sur 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱3,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Brgy. La Medalla, Baao, Camarines Sur
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-17-0010836

₱277,253.00 · FY2017

Released to Salvacion National High School - Bato (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

352 projects · ₱28.1B total · 0 flags

4. Implementation

Contract Amount

₱97,000,000.00

Progress

Reported complete (DPWH)

Start Date

January 4, 2018

Target End

September 2, 2018

5. Audit