Flood Control and Drainage18GJ0108

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF SLOPE PROTECTION WORKS AND IMPROVEMENT ALONG ILOILO RIVER, RIGHT BANK (FROM MUELLELONEY BRIDGE (RIZAL) TO MUELLELONEY BRIDGE (DRILON BRIDGE)), ILOILO CITY

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF SLOPE PROTECTION WORKS AND IMPROVEMENT ALONG ILOILO RIVER, RIGHT BANK (FROM MUELLELONEY BRIDGE (RIZAL) TO MUELLELONEY BRIDGE (DRILON BRIDGE)), ILOILO CITY is a DPWH-tracked public work in Iloilo City DEO, Region VI. Reported contract value: ₱24,499,396.39. Status: Reported complete (DPWH). Contractor on record: IBC INTERNATIONAL BUILDERS CORP. Figures trace to dpwh.

Iloilo City DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Slope Protection works and Improvement along Iloilo River, Right Bank (from Muelle Loney Bridge (Rizal) to Muelle Loney Bridge (Drilon Bridge)), Iloilo City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-18-0033578

₱0.00 · FY2018

Released to Division of Ilocos Sur (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱24,499,396.39

Progress

Reported complete (DPWH)

Start Date

March 22, 2018

Target End

January 11, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.