Roads17FA0018

CLUSTER 8-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS AND DECLARED TOURISM DESTINATIONS:ACCESS ROADS LEADING TO BARANGAY 3 SEAPORT, MALILIPOT,ALBAY AND LEADING TO BUHATAN SEAPORT, STO. DOMINGO, ALBAY 1ST LD

CLUSTER 8-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS AND DECLARED TOURISM DESTINATIONS:ACCESS ROADS LEADING TO BARANGAY 3 SEAPORT, MALILIPOT,ALBAY AND LEADING TO BUHATAN SEAPORT, STO. DOMINGO, ALBAY 1ST LD is a DPWH-tracked public work in Albay 1st DEO, Region V. Reported contract value: ₱68,110,000.00. Status: Reported complete (DPWH). Contractor on record: MAKAPA CORP. Figures trace to dpwh.

Albay 1st DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

123 projects · ₱9.7B total · 0 flags

Other projects by this contractor

No sat.

OO2-PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION/REHABILITATION OF NASISI RIVER FLOOD MITIGATION STRUCTURE(BRGY. CAVASI AND BRGY. TOMOL

Region V, Region V

2022₱192.9M
Past target date (DPWH On-Going)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS:CONST./IMPV'T. OF CADAC-AN RIVER FLOOD CONTROL SYSTEM,JUBAN, SORSOGON

Region V, Region V

2018₱185.2M
Reported complete (DPWH)

Construction/Improvement/Rehabilitation of Cadac-an River Flood Mitigation Structure, Sta. 12+260 - Sta. 12+308 Right Side, Sta. 11+792 - Sta. 12+848 Left Side, Juban, Sorsogon

JUBAN (SORSOGON), SORSOGON, Region V

2022₱174.7M
Reported complete (DPWH)

Construction/Improvement/Rehabilitation of Cadac-an River Flood Mitigation Structure, Sta. 23+752.00 - Sta. 24+575.57 Left Side, Sta. 23+806.50 - Sta. 24+357.50 Right Side, Irosin, Sorsogon

IROSIN (SORSOGON), SORSOGON, Region V

2022₱174.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, NABONTON RIVER, LIGAO CITY, ALBAY

Region V, Region V

2025₱173.6M
Past target date (DPWH On-Going)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS:CONST.OF FLOOD MITIGATION STRUCTURES ALONG SAN AGUSTIN RIVER,LIBON AL

Region V, Region V

2018₱171.0M
Reported complete (DPWH)
View all 123 projects →

4. Implementation

Contract Amount

₱68,110,000.00

Progress

Reported complete (DPWH)

Start Date

March 6, 2017

Target End

October 18, 2017