Construction of Flood Mitigation Structure23D00158

Construction of Revetment along Ylang-Ylang River, Buenavista, Gen. Trias, Cavite (Phase IV)

Construction of Revetment along Ylang-Ylang River, Buenavista, Gen. Trias, Cavite (Phase IV) is a DPWH-tracked public work in CITY OF GENERAL TRIAS (CAVITE), CAVITE, Region IV-A. Reported contract value: ₱96,498,165.29. Status: Reported complete (DPWH). Contractor on record: I&E CONST CORP FORMERLY: I&E CONSTR / MOTIONTRADE DEVELOPMENT CORP. Figures trace to sumbong.

CITY OF GENERAL TRIAS (CAVITE), CAVITE, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱37,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures, Road and Other Improvements in Palico 4, Imus, Cavite
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cavite 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,498,165.29

Progress

Reported complete (DPWH)

Start Date

July 7, 2023

Target End

April 1, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.