Roads19FJ0033

LOCAL INFRASTRUCTURE PROGRAM, CONSTRUCTION OF CONCRETE ROAD-CONCRETING OF DAPDAP-SIMAWA ROAD, USON, MASBATE

LOCAL INFRASTRUCTURE PROGRAM, CONSTRUCTION OF CONCRETE ROAD-CONCRETING OF DAPDAP-SIMAWA ROAD, USON, MASBATE is a DPWH-tracked public work in Masbate 3rd DEO, Region V. Reported contract value: ₱18,630,873.67. Status: Reported complete (DPWH). Contractor on record: ARKY CONST AND SUPPLY. Figures trace to dpwh.

Masbate 3rd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROII-19-0008997

₱33,537.00 · FY2019

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

76 projects · ₱4.0B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES-BALUD NATIONAL ROAD CONNECTING BARANGAY DANAO IN SUPPORT OF AGRIBUSINESS, BALUD, MASBATE PROVINCE

Region V, Region V

2018₱179.1M
Reported complete (DPWH)
No sat.

CONST./REPAIR/REHAB./IMPVT. OF SWANG-AGPANABAT ROAD, ROMBLON, ROMBLON STA.15+290-STA.15+603.35, STA.15+877.92-STA. 16+637.30 STA.16+895.50-STA. 17+208.80, STA.17+500.00-STA.-STA.17+857.80 STA. 18+295.80-STA.20+513.60, STA. 20+660.00-STA.21+617.00 W/EXCEPT

Region IV-B, Region IV-B

2016₱168.4M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-SECONDARY ROADS-MASBATE-CATAINGAN-PLACER ROAD, MASBATE PROVINCE

Region V, Region V

2018₱155.6M
Reported complete (DPWH)
No sat.

ROAD UPGRADING OF SIBUYAN CIRC RD K0023+563-K0025+487; K0025+524-K0026+198; K0027+1086-K0029+237; SI

Region IV-B, Region IV-B

2016₱146.2M
Reported complete (DPWH)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED) OF SIBUYAN CIRCUM. RD., KO029+237-KO030+346; KO030+408-KO031+364; KO031+431-KO031+497; KO031+571-KO031+638; KO032+555-KO033+073; KO033+086-KO033+615; KO034+094-KO035+690; KO035+908-KO036+528, SIBUYAN IS., ROMBLON

Region IV-B, Region IV-B

2016₱145.8M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF MISSING LINKS/NEW ROADS, SAN FERNANDO-SAN JACINTO-MONREAL ROAD, MASBATE, TICAO ISLAND, MASBATE

Region V, Region V

2018₱144.7M
Reported complete (DPWH)
View all 76 projects →

4. Implementation

Contract Amount

₱18,630,873.67

Progress

Reported complete (DPWH)

Start Date

July 17, 2019

Target End

October 26, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.