Flood Control and Drainage22CC0279

REHABILITATION OF GUIGUINTO RIVER, STA. 01+281 TO STA. 01+666, BRGY. DAUNGAN, GUIGUINTO, BULACAN

REHABILITATION OF GUIGUINTO RIVER, STA. 01+281 TO STA. 01+666, BRGY. DAUNGAN, GUIGUINTO, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱48,998,962.01. Status: Reported complete (DPWH). Contractor on record: WAWAO BUILDERS. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱46,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures along Guiguinto River, Malis Section, Guiguinto, Bulacan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Bulacan 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

F

164 projects · ₱9.2B total · 15 flags

4. Implementation

Contract Amount

₱48,998,962.01

Progress

Reported complete (DPWH)

Start Date

April 5, 2022

Target End

January 29, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.