Contractor Concentration (Flood Control)

A contractor holds a very large share of flood-control contract value in a district or province.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: LEGACY CONST CORP FORMERLY: LEGACY CONST received 57.3% (₱1.77B of ₱3.09B) of recorded flood-control contract value in Negros Occidental 2nd District Engineering Office across 40 contracts and 11 contractors, at or above the 25% share threshold (HHI 0.362). This may be due to the contractor's specialized expertise or limited competition in the area.

Public record entityLEGACY CONST CORP FORMERLY: LEGACY CONSTOrganization record →
LocationNegros Occidental 2nd District Engineering Office
Amount₱1,771,572,747.5457.3% of peer-group contract value in public records sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Flagged peer group: Negros Occidental 2nd District Engineering Office

Reported complete (DPWH): 23Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Binalbagan River Bank Slope Protection (Downstream of Alicante Bridge), Phase II, Left Bank, Along Jct Bagonawa-La Castellana-Isabela Road, Isabela, Negros Occidental22GL0094100%March 28, 2023March 28, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Binalbagan River Bank Slope Protection (Downstream of Alicante Bridge), Phase II, Right Bank, Along Jct Bagonawa-La Castellana-Isabela Road, Isabela, Negros Occidental22GL0097100%March 6, 2023March 6, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Binalbagan River Bank Slope Protection (Upstream of Alicante Bridge), Phase II, Right Bank, Along Jct Bagonawa-La Castellana-Isabela Road, Isabela, Negros Occidental22GL0095100%March 20, 2023March 20, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Binalbagan River Bank Slope Protection along Binalbagan-Isabela Road, Brgy. San Jose, Binalbagan, Negros Occidental (Phase 3)23GL0066100%February 14, 2024February 14, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Binalbagan River Bank Slope Protection along Jct. Bagonawa - La Castellana - Isabela road Brgy. 5 Poblacion, Isabela, Negros Occidental24GL0041100%October 11, 2024August 5, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Binalbagan River Bank Slope Protection at Barangay Canmuros, Binalbagan, Negros Occidental24GL0047100%December 4, 2024October 22, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Show 17 more projects in this bucket
Construction of Binalbagan River Bank Slope Protection at Had. Millan, Brgy. Rumirang, Isabela, Negros Occidental24GL0042100%October 11, 2024August 5, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Binalbagan River Bank Slope Protection Downstream of Binalbagan (Bagacay) Br. Right Bank, Phase II, Isabela, Negros Occidental22GL0098100%November 24, 2022November 22, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Binalbagan River Bank Slope Protection Downstream of Binalbagan (Bagacay) Bridge along Hinigaran-Isabela Road, Brgy. Aranda (Phase IV, Left Bank), Hinigaran, Negros Occidental23GL0079100%October 5, 2023October 5, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Binalbagan River Bank Slope Protection Upstream of Alicante Bridge along Jct. Bagonawa-La Castellana-Isabela Road, Barangay Bungahin, (Phase IV, Right Bank), Isabela, Negros Occidental23GL0072100%February 11, 2024February 11, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Binalbagan River Bank Slope Protection Upstream of Binalbagan Bridge along Bacolod South Road, Brgy. Palayog (Phase IV, Left Bank) Hinigaran, Negros Occidental23GL0062100%December 13, 2023December 13, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Binalbagan River Bank Slope Protection Upstream of Binalbagan Bridge along Bacolod South Road, Brgy. San Jose (Phase IV, Right Bank) Binalbagan, Negros Occidental23GL0076100%December 18, 2023December 18, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Binalbagan Riverbank Slope (Downstream of Binalbagan Bridge) along Bacolod South Road (Right Bank), Negros Occidental22GL0043100%December 13, 2022December 13, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Camansi River Bank Slope Protection Dowstream of Camansi Bridge along Jct Pontevedra - La Castellana Road (Left Bank), Barangay Robles, La Castellana, Negros Occidental23GL0039100%January 4, 2024January 4, 2024No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Camansi River Bank Slope Protection Upstream of Camansi Bridge along Jct Pontevedra - La Castellana Road (Left Bank), Barangay Robles, La Castellana, Negros Occidental23GL0037100%December 24, 2023December 24, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Grouted Rip Rap and Line Canal along Bacolod South Road, K0060+550 - K0061+300 and K0064+800 - K0065+250 with exceptions, Binalbagan, Negros Occidental22GL0059100%September 13, 2022September 13, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Grouted Rip Rap and Line Canal along Jct Bagonawa - La Castellana - Isabela Road, K0069+000 - K0070+100 with exceptions, La Castellana, Negros Occidental22GL0060100%September 14, 2022August 15, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Guintubhan River Bank Slope (Downstream of Guintubhan Br.) along Binalbagan - Isabela Road (Left Bank, Phase II), Negros Occidental22GL0092100%January 19, 2023January 17, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Guintubhan River Bank Slope (Upstream of Guintubhan Br.) along Binalbagan - Isabela Road (Right Bank, Phase II), Negros Occidental22GL0093100%January 19, 2023January 19, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Guintubhan River Bank Slope (Upstream of Guintubhan Bridge) along Binalbagan - Isabela Road (Left Bank, Phase II), Negros Occidental22GL0038100%March 10, 2023March 9, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of River Bank Slope Protection along Indurayan River, Downstream of Indurayan Bridge Left Bank, La Castellana, Negros Occidental22GL0101100%April 1, 2023April 1, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of River Bank Slope Protection along Indurayan River, Downstream of Indurayan Bridge Right Bank, La Castellana, Negros Occidental22GL0099100%March 29, 2023March 29, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source
Construction of Su-ay Riverbank Slope Protection (Upstream/left bank of Su-ay Bridge) along Bacolod South Rd. Barangay Su-ay, Himamaylan City, Negros Occidental22GL0041100%November 15, 2022December 12, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source

Rule Definition

Share of contract value by contractor within DEO or province; flags top share > 40% or elevated HHI.

Triggering Data & citations

Contractor holds a large share of flood-control contract value in its district/province

{
  "hhi": 0.3620129936623835,
  "scope": "deo",
  "bucketKey": "deo:Negros Occidental 2nd District Engineering Office",
  "contractor": "LEGACY CONST CORP FORMERLY: LEGACY CONST",
  "thresholds": {
    "share": 0.25,
    "minContracts": 3,
    "minBucketContracts": 10
  },
  "bucketTotalPhp": 3092963482.82,
  "contractorShare": 0.5727751903248381,
  "contractorTotalPhp": 1771572747.54,
  "contractorContracts": 23
}

Possible Innocent Explanations

  • This may be due to the contractor's specialized expertise or limited competition in the area.

Connected records

Where this contractor works

Contractor grade B20 storms reached its projects · typhoon modeAll contractors & gradesContractor patterns